Project Description

Synopsis: Strengthen the 25m x 50m long sagged slab

Action Taken

Due to early removing of shuttering the 25m x 50m long slab got 100m sagged which becomes inadequate for the structure to bear the designed load. With the help of Pre-stress system the slab was up-lifted back by stretching the CFK Laminates at a pre-stress pressure of 10 tons and anchored on both ends with High tensioned anchor plates.